SPP-ERAS-2025-012
750 MW generation in Mercer, ND · In queue since October 2025 · Proposed COD September 2030
750 MW
Capacity
1
Components
Gas
1y 1m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Study Phase
ERAS-2025-001; 01 NORTH
Interconnection request submitted to ISO/RTO
IA PENDING
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-27
About
Generated Apr 10, 2026 · Predates Oct 22, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
SPP-ERAS-2025-012 is a proposed 750 MW natural gas-fired generation project located in Stanton County, North Dakota. The project, utilizing combined cycle technology, is being developed by BEPC and is interconnected within the Southwest Power Pool (SPP) at the Leland Olds 345kV Substation.
The project entered the SPP interconnection queue on October 1, 2025, seeking Energy Resource and Network Resource (ER/NR) service. As of the latest data, the project's interconnection status is listed as active.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- SPP queue source as of: Oct 22, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Mercer
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
BEPC
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Leland Olds 345kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WAUE.BEPM.LOS1
- POI Substation
- 345/230kV Leland Olds Switchyard Addition
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
GSPP Held LLC CSG
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
NE Renewable Power West Enfield
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
GSPP 409 Ferris Road
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.