SPP-ERAS-2025-011
750 MW generation in Mercer, ND · In queue since October 2025 · Proposed COD September 2030
750 MW
Capacity
1
Components
Gas
9 months
In Queue
In Progress (unknown study)
IA Phase
COD target: 2030
Total Duration
4y 11m
Study Phase
ERAS-2025-001; 01 NORTH
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-27
SPP-ERAS-2025-011 is a proposed 750 MW natural gas-fired generation project located in Stanton County, North Dakota. The project, which utilizes combined cycle technology, is being developed by BEPC and is interconnected to the Leland Olds 345kV Substation.
The project is currently active in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on October 1, 2025. It is seeking ER/NR service type.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ND
County
Mercer
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
BEPC
Entity
SPP
Service Type
NRIS/ERIS
Point of Interconnection
Leland Olds 345kV Substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WAUE.BEPM.LOS1
- POI Substation
- 345/230kV Leland Olds Switchyard Addition
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-ERAS-2025-011Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.