SPP-ASGI-2021-001
50 MW generation in — · In queue since April 2021
50 MW
Capacity
0
Components
5y 6m
In Queue
—
IA Status
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ASGI-2021-001 is a proposed hybrid solar and battery storage generation project in the Southwest Power Pool (SPP) interconnection queue. The development project has a total capacity of 50 MW and is classified in the queue as a hybrid solar/storage facility. The available data do not identify the project's developer, its county and state, or the individual capacities of its solar and battery components.
The project entered the SPP queue on April 26, 2021, and remains active. It has requested both Energy Resource (ER) and Network Resource (NR) interconnection service. The "ASGI" designation in the queue ID refers to SPP's process for Affected System Generator Interconnection requests. The provided data include no proposed commercial operation date, interconnection agreement status, link to an existing operating plant in EIA records, or recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
SPP
Service Type
ER/NR
Data Source
Live · SPP
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SPP
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SPP-ASGI-2021-001Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.