120 MW generation in Oglethorpe, GA · In queue since October 2021 · Proposed COD April 2025
120 MW
Capacity
1
Components
Solar
5y 1m
In Queue
—
IA Status
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-30
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
SOCO-IC-988 is a proposed solar generation project with a total capacity of 120 MW, located in Oglethorpe County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on October 21, 2021, with a proposed commercial operation date of April 30, 2025. Its interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) is the East Watkinsville - Russell Dam (USA) 230 kV Line. The project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Oglethorpe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
ERIS
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Georgia Power at Wadley GA
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Swainsboro
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Jakin GA PV
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.