SOCO-IC-933
250 MW hybrid in Glynn, GA · In queue since December 2020 · Proposed COD February 2024
250 MW
Capacity
1
Components
Solar
5y 7m
In Queue
—
IA Status
COD target: 2024
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-24
SOCO-IC-933 is a proposed 380 MW hybrid solar and battery project located in Glynn County, Georgia. The development project, located in the Southeast region, consists of a 250 MW solar component and a 130 MW battery energy storage system. The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of December 21, 2020, and a proposed commercial operation date of February 24, 2024.
The interconnection status for SOCO-IC-933 is currently listed as "Suspended." The point of interconnection is the Thalmann TS 230 kV Bus.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Glynn
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
NRIS
Point of Interconnection
Thalmann TS 230 kV Bus
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-IC-933Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.