SOCO-IC-696
250 MW generation in Sumter, GA · In queue since May 2018 · Proposed COD April 2023
250 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-04-01
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
SOCO-IC-696 is a proposed 500 MW solar generation project located in Sumter County, Georgia. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 500 MW of solar photovoltaic generation.
The project is listed in the Southern Company (SOCO) interconnection queue with an entry date of May 3, 2018. The proposed commercial operation date is April 1, 2023, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Fortson - North Tifton 500 kV Line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Sumter
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
NRIS
Point of Interconnection
Fortson - North Tifton 500 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Georgia Power at Wadley GA
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Swainsboro
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Georgia Power at Jakin GA PV
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.