SOCO-IC-695
250 MW generation in Sumter, GA · In queue since May 2018 · Proposed COD April 2023
250 MW
Capacity
1
Components
Solar
8y 2m
In Queue
IA Executed
IA Phase
COD target: 2023
Total Duration
4y 11m
Schedule
40 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-04-01
The proposed SOCO-IC-695 project is a 250 MW solar generation facility in Sumter County, Georgia. The project is being developed by SOCO, a subsidiary of Southern Company. It consists of 250 MW of solar photovoltaic generation.
The project is in the Southern Company (SOCO) interconnection queue, with an original queue entry date of May 3, 2018. The proposed commercial operation date is April 1, 2023, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the Fortson - North Tifton 500 kV Line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Sumter
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
NRIS
Point of Interconnection
Fortson - North Tifton 500 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-IC-695Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.