SOCO-IC-1100
450 MW hybrid in Pulaski, GA · In queue since November 2022 · Proposed COD June 2026
450 MW
Capacity
2
Components
Solar + Battery
3y 6m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-28
SOCO-IC-1100 is a proposed 450 MW hybrid solar and battery project located in Pulaski County, Georgia. The development project, located in the Southeast region, consists of a 300 MW solar component and a 150 MW battery energy storage system. The project is being developed within the Southern Company (SOCO) interconnection queue, with an initial queue entry date of November 29, 2022, and a proposed commercial operation date of June 28, 2026.
The interconnection status for SOCO-IC-1100 is currently listed as "Suspended". The point of interconnection (POI) is the Kathleen - Pitts 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Pulaski
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Kathleen - Pitts 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.