SOCO-IC-1086
80 MW hybrid in Perry, AL · In queue since November 2022 · Proposed COD July 2026
80 MW
Capacity
1
Components
Solar
3y 8m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-15
SOCO-IC-1086 is a proposed 160 MW hybrid solar and battery project located in Perry County, Alabama. The development project, with Southern Company (SOCO) as the interconnecting entity, consists of 80 MW of solar capacity coupled with 80 MW of battery storage. It is listed as active in the Southern Company (SOCO) interconnection queue with an entry date of November 2, 2022.
The proposed commercial operation date for SOCO-IC-1086 is July 15, 2026. The interconnection agreement (IA) status is currently listed as Suspended. The point of interconnection (POI) is the Greene County - North Selma 230 kV Line.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AL
County
Perry
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
ERIS
Point of Interconnection
Greene County - North Selma 230 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-IC-1086Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.