SOCO-IC-1005
100 MW generation in Burke, GA · In queue since December 2021 · Proposed COD October 2026
100 MW
Capacity
1
Components
Solar
4y 7m
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
SOCO-IC-1005 is a proposed 100 MW solar generation project located in Burke County, Georgia. The project, developed by Southern Company (SOCO), entered the Southern Company (SOCO) interconnection queue on December 14, 2021, with a proposed commercial operation date of October 1, 2026. The point of interconnection is the Waynesboro Primary - Wilson 230 kV Line. The interconnection agreement status is currently listed as Suspended.
The proposed project consists of 100 MW of solar photovoltaic generation capacity. It is currently listed as an active project within the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Burke
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
ERIS
Point of Interconnection
Waynesboro Primary - Wilson 230 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-IC-1005Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.