SOCO-IC-1001
80 MW generation in Early, GA · In queue since December 2021 · Proposed COD August 2025
80 MW
Capacity
1
Components
Solar
4y 7m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-20
SOCO-IC-1001 is a proposed 80 MW solar generation project located in Early County, Georgia. The project is being developed by SOCO and is interconnected within the Southern Company (SOCO) queue, with an interconnection queue entry date of December 8, 2021. The proposed commercial operation date is August 20, 2025.
The interconnection agreement (IA) status for SOCO-IC-1001 is currently listed as Suspended. The point of interconnection (POI) is the Blakely Primary - Webb 115 kV Line. The project has appeared in recent news coverage regarding solar development in the Southeast.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
GA
County
Early
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
ERIS
Point of Interconnection
Blakely Primary - Webb 115 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-IC-1001Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.