SOCO-25-IC-1380
200 MW hybrid in Escambia, AL · In queue since April 2025 · Proposed COD October 2028
200 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Cluster Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-15
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
SOCO-25-IC-1380 is a proposed hybrid solar and battery storage development project located in Escambia County, Alabama, in the southeastern United States. The project has a total capacity of 200 MW, and its solar component accounts for the full 200 MW. A battery storage component is also listed, but no separate capacity figure is given for it. No developer is identified in the available data. The project would interconnect with the transmission system of Southern Company at a point of interconnection on the Honeybee (NextEra) – North Brewton 230 kV line.
The project entered the Southern Company (SOCO) interconnection queue on April 17, 2025, and its status is currently active. It has requested Energy Resource Interconnection Service (ERIS) and is in the Cluster Study phase of the interconnection process. No interconnection agreement has been executed. The proposed commercial operation date is October 15, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
AL
County
Escambia
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
ERIS
Point of Interconnection
Honeybee (NextEra) - North Brewton 230 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project SOCO-25-IC-1380Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.