S-C-234
75 MW storage in Hampton, SC · In queue since June 2023 · Proposed COD October 2027
75 MW
Capacity
1
Components
Battery
3y 1m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
4y 4m
Study Phase
2023 Cluster
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
S-C-234 is a proposed 75 MW battery storage project located in Hampton County, South Carolina. The project is being developed within the Santee Cooper (S-C) interconnection queue, with an initial queue entry date of June 1, 2023. The current interconnection status is listed as "In Progress (unknown study)".
The proposed commercial operation date (COD) for the battery storage project is October 31, 2027. The project consists of 75 MW of battery capacity.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
SC
County
Hampton
Grid Region
Southeast
Market
—
Developer
—
Utility
Santee Cooper
Entity
S-C
Service Type
NRIS
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project S-C-234Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.