PSCo-GI-2024-19
199 MW hybrid in Lincoln, CO · In queue since May 2024 · Proposed COD May 2028
199 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4 years
Study Phase
DISIS-2024-007
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-05
The PSCo-GI-2024-19 development project is a proposed 199 MW hybrid solar and battery energy storage project located in Lincoln County, Colorado. The project consists of 199 MW of solar photovoltaic generation. It is interconnected to the Public Service Company of Colorado (PSCo) via the Pronghorn-Missile Site 345 kV line.
The project is currently active in the PSCo interconnection queue, with an entry date of May 17, 2024. The proposed commercial operation date is May 5, 2028. The project has appeared in recent news coverage regarding renewable energy development in the Western United States.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
NRIS
Point of Interconnection
Pronghorn-Missile Site 345 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSCo-GI-2024-19Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.