PSCo-GI-2024-07
100 MW hybrid in Pueblo, CO · In queue since May 2024 · Proposed COD May 2028
100 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4 years
Study Phase
DISIS-2024-007
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-15
The proposed PSCo-GI-2024-07 project is a 100 MW solar and battery hybrid development in Pueblo County, Colorado. The project consists of 100 MW of solar generation. It is located in the West region and is being proposed by Public Service Company of Colorado (PSCo).
The project is currently active in the Public Service Company of Colorado interconnection queue, with an entry date of May 10, 2024. The proposed commercial operation date is May 15, 2028. The point of interconnection is the Comanche 115 kV Substation.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
NRIS
Point of Interconnection
Comanche 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.