PSCo-GI-2023-14
400 MW generation in Morgan, CO · In queue since May 2023 · Proposed COD October 2026
400 MW
Capacity
1
Components
Wind
3y 2m
In Queue
Suspended
IA Phase
COD target: 2026
Total Duration
3y 5m
Study Phase
DISIS-2023-006
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
PSCo-GI-2023-14 is a proposed 400 MW wind generation project located in Morgan County, Colorado. The project, under development by Public Service Company of Colorado (PSCo), entered the Public Service Company of Colorado interconnection queue on May 22, 2023. Its proposed commercial operation date is October 1, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 400 MW of wind generation capacity. The point of interconnection is the Pawnee Substation at 345 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Morgan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
NRIS
Point of Interconnection
Pawnee Substation 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSCo-GI-2023-14Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.