PSCo-GI-2020-10
230 MW hybrid in Pueblo, CO · In queue since April 2020 · Proposed COD December 2023
230 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Suspended
IA Phase
COD target: 2023
Total Duration
3y 8m
Study Phase
DISIS-2020-001
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
The proposed PSCo-GI-2020-10 project is a 230 MW solar and battery hybrid development in Pueblo County, Colorado. Interconnecting to the Public Service Company of Colorado (PSCo) via the Comanche-Midway 230 kV line, the project entered the PSCo interconnection queue on April 7, 2020, with a proposed commercial operation date of December 1, 2023. The project consists of 230 MW of solar capacity.
The project's interconnection status is currently listed as "suspended," and its Interconnection Agreement (IA) status is also "suspended." The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
NRIS
Point of Interconnection
Comanche-Midway 230 kV line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSCo-GI-2020-10Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.