Project PSCo-5RSC-2024-09 — Project Summary

Queue ID
PSCo-5RSC-2024-09
Capacity
200 MW
Technology
Battery
Status
active
Location
Park, CO
Region
West
Developer
IA Status
In Progress (unknown study)

PSCo-5RSC-2024-09

PSCo-5RSC-2024-09BetaActiveBatteryPSCoLBNL

200 MW storage in Park, CO · In queue since January 2024 · Proposed COD December 2027

200 MW

Capacity

1

Components

Battery

2y 4m

In Queue

In Progress (unknown study)

IA Phase

COD target: 2027

Interconnection

Total Duration

3y 11m

Study Phase

5RSC-2024

In Study38%
Queue EntryJan 24, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

CO

County

Park

Grid Region

Mountain West

Market

Developer

Utility

Public Service Company Of Colorado

Entity

PSCo

Service Type

ERIS

Point of Interconnection

Hartsel 230 kV Substation

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
No news available for this project.

No Ask reports yet for this entity.

Ask about Project PSCo-5RSC-2024-09
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.