PSCo-2RSC-2020-05
250 MW hybrid in Pueblo, CO · In queue since September 2020 · Proposed COD September 2022
250 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Phase
COD target: 2022
Total Duration
2 years
Schedule
46 months past proposed COD
Study Phase
2RSC-2020
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-09-30
PSCo-2RSC-2020-05 is a proposed 250 MW hybrid solar and battery project located in Pueblo County, Colorado. The development project, consisting of 250 MW of solar capacity, is in the Public Service Company Of Colorado (PSCo) interconnection queue, with an interconnection queue entry date of September 10, 2020. The proposed commercial operation date is September 30, 2022. The interconnection agreement has been executed.
The point of interconnection (POI) for the project is the Mirasol Switchyard on the Comanche-Midway 230 kV Transmission Line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
ERIS
Point of Interconnection
Mirasol Switchyard on the Comanche- Midway 230 kV Transmission Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSCo-2RSC-2020-05Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.