PSCo-1RSC-2020-02
75 MW storage in Pueblo, CO · In queue since January 2020 · Proposed COD December 2022
75 MW
Capacity
1
Components
Battery
6y 6m
In Queue
IA Executed
IA Phase
COD target: 2022
Total Duration
2y 11m
Schedule
44 months past proposed COD
Study Phase
1RSC-2020
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2022-12-01
The proposed PSCo-1RSC-2020-02 project is a 75 MW battery storage development in Pueblo County, Colorado. The project is interconnected to the Public Service Company of Colorado (PSCo) via the Comanche-Daniels Park 345 kV point of interconnection.
The project is listed in the PSCo interconnection queue with an entry date of January 24, 2020. The proposed commercial operation date is December 1, 2022, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
CO
County
Pueblo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company Of Colorado
Entity
PSCo
Service Type
ERIS
Point of Interconnection
Comanche-Daniels Park 345 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PSCo-1RSC-2020-02Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.