Corazon Energy Storage
150 MW storage in Bernalillo, NM · In queue since July 2021 · Proposed COD June 2024
150 MW
Capacity
1
Components
Battery
5y 4m
In Queue
IA Executed
IA Phase
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 11m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-06-01
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with PNM, queue position PNM-IA-PNM-2021-13
prnewswire.com20-year physical PPA awarded by Public Service Company of New Mexico to Plus Power
prnewswire.comResearch sources and reasoning (1 recorded sources)
high confidence at research time
Commercial operation date: LBNL proposed COD of June 2024 is stale. PR Newswire article from Nov 2024 indicates PPA award was just won, suggesting project is in early development with COD likely 2026+ based on typical 18-24 month battery storage construction timelines after PPA execution.
Developer: LBNL snapshot has null developer field. PR Newswire press release from Nov 2024 clearly identifies Plus Power as the developer and PPA seller for this project.
Status: LBNL shows 'active' status with IA executed. Nov 2024 press release confirms PPA award from Public Service Company of New Mexico, indicating project is advancing through development milestones.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Corazon Energy Storage is a proposed 150 MW battery storage project located in Bernalillo County, New Mexico. The project, developed by an unknown entity, is interconnected to the Public Service Company of New Mexico (PNM) via the Pajarito 345 kV Substation. It entered the PNM interconnection queue as project number PNM-IA-PNM-2021-13 on July 12, 2021, with a proposed commercial operation date of June 1, 2024. The project's interconnection agreement (IA) has been executed.
The Corazon Energy Storage project has been featured in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
ERIS
Point of Interconnection
Pajarito 345 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26