Old Route 66 Power
200 MW generation in Guadalupe, NM · In queue since June 2021 · Proposed COD November 2024
200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Phase
COD target: 2024
Total Duration
3y 5m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-11-01
The proposed project PNM-IA-PNM-2021-08 is a 200 MW solar generation project located in Guadalupe County, New Mexico. The developer is PNM (Public Service Company of New Mexico). It consists of 200 MW of solar photovoltaic generation.
The project is in the Public Service Company of New Mexico interconnection queue, with an entry date of June 11, 2021. The proposed commercial operation date is November 1, 2024, and the Interconnection Agreement (IA) status is currently listed as "IA Pending." The point of interconnection is the Taiban-345 kV Line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Guadalupe
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
NRIS
Point of Interconnection
Taiban- 345 kV Line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Old Route 66 PowerForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.