PNM-IA-PNM-2020-17
150 MW storage in Bernalillo, NM · In queue since September 2020 · Proposed COD January 2023
150 MW
Capacity
1
Components
Battery
6y 2m
In Queue
IA Executed
IA Phase
COD target: 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 4m
Schedule
47 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2023-01-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed with PNM, queue position secured
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2023-01-01. No independent sources to verify if this date was met or updated. Project is marked active with IA executed but not operational as of snapshot date.
Developer: LBNL lists 'AES Renewable Holdings' which appears to be the parent operating company rather than a project-specific LLC. No alternative sources available to verify or identify a shell entity.
Status: LBNL shows IA executed with active queue status but is_operational=false. Without news sources, cannot determine if project achieved 2023 COD or current construction/operational state.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PNM-IA-PNM-2020-17 is a proposed 150 MW battery storage project located in Bernalillo County, New Mexico. The project, being developed by AES Renewable Holdings, is interconnected to the Public Service Company of New Mexico (PNM) via the Petroglyph 115 kV Substation.
The project is in the PNM interconnection queue, with an entry date of September 22, 2020. The proposed commercial operation date is January 1, 2023, and the Interconnection Agreement (IA) has been executed.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Bernalillo
Grid Region
Mountain West
Market
—
Developer
AES Renewable Holdings
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
—
Point of Interconnection
Petroglyph 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
AES queue pipeline by technology
Comparative analysis covering fleet scale, performance trends, and growth pipeline.
AES Baird Solar CSG
Data-driven briefing on AES — fleet, generation, financial, and news signals.
AES ES GILBERT
Data-driven briefing on AES — fleet, generation, financial, and news signals.
AES Petersburg
Data-driven briefing on AES — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.