PNM-IA-PNM-2019-12
80 MW generation in Torrance, NM · In queue since April 2019 · Proposed COD September 2020
80 MW
Capacity
1
Components
Wind
7y 3m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2020
Total Duration
1y 5m
Schedule
71 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-09-01
The proposed project, identified as PNM-IA-PNM-2019-12, is an 80 MW wind generation facility in Torrance County, New Mexico. The project is being developed within the Public Service Company of New Mexico (PNM) service area. It is interconnected to the Clines Corners 345 kV Switching Station.
The project entered the PNM interconnection queue on April 23, 2019, with a proposed commercial operation date of September 1, 2020. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NM
County
Torrance
Grid Region
Mountain West
Market
—
Developer
—
Utility
Public Service Company of New Mexico
Entity
PNM
Service Type
ERIS
Point of Interconnection
Clines Corners 345 kV Switching Station
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PNM-IA-PNM-2019-12Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.