Pickens 138 kV
168 MW generation in Randolph, WV · In queue since April 2026 · Proposed COD October 2030
168 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-31
The Pickens 138 kV project (PJM queue ID PJM-C01-2153) is a proposed 168 MW wind generation project in Randolph County, West Virginia. The development project is being pursued by Twinleaf Wind Power, LLC. It would connect to the transmission system at the Pickens 138 kV point of interconnection, located within the service territory of APS.
The project is listed in the interconnection queue of PJM Interconnection, the regional transmission organization serving the area, under the Generation Interconnection service type. It entered the queue on April 24, 2026, and is currently active. It is being evaluated in the C01 study phase, part of PJM's cycle-based interconnection process. The proposed commercial operation date is October 31, 2030. The available data does not indicate an executed interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Twinleaf Wind Power, LLC
Utility
APS
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Pickens 138 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PICKENS 138 KV T1
- POI Substation
- Pickens Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Pickens 138 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.