South Justice - Dawsons Crossroads DP 115 kV
100 MW generation in Halifax, NC · In queue since April 2026 · Proposed COD February 2031
100 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 10m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-07
South Justice - Dawsons Crossroads DP 115 kV (queue ID PJM-C01-2145) is a proposed solar and battery storage hybrid development project in Halifax County, North Carolina. The project is being developed by Beech Sapling Solar LLC and has a total proposed capacity of 100 MW. The provided data does not break this total down into separate solar and storage capacities. The project would connect to the grid at the South Justice - Dawsons Crossroads DP 115 kV point of interconnection, within the Dominion utility service territory.
The project is listed as active in the PJM Interconnection queue, which it entered on April 27, 2026, under a Generation Interconnection service request. It is currently in study phase C01 of PJM's interconnection process. The proposed commercial operation date is February 7, 2031. The available data does not indicate the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Beech Sapling Solar LLC
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
South Justice - Dawsons Crossroads DP 115 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about South Justice - Dawsons Crossroads DP 115 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.