West Landing 230 kV
300 MW storage in Chesapeake, VA · In queue since April 2026 · Proposed COD March 2031
300 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-14
West Landing 230 kV is a proposed 300 MW battery energy storage project located in Chesapeake, Virginia. The development project is being pursued by Bayberry Energy, LLC and would connect to the transmission system operated by Dominion at the West Landing 230 kV point of interconnection. It is classified as a standalone storage project, with no additional generation components identified in the available data.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-2101, with a queue entry date of April 27, 2026. It is requesting Generation Interconnection service and is in study phase C01. The project's status in the queue is active, and its proposed commercial operation date is March 14, 2031. The available data does not report an interconnection agreement status.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Chesapeake
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Bayberry Energy, LLC
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
West Landing 230 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WESTLNDG34.5 KV TX2
- POI Substation
- West Landing Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about West Landing 230 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.