Gary 25 kV
42 MW generation in Lunenburg, VA · In queue since April 2026 · Proposed COD October 2030
42 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-31
Gary 25 kV is a proposed 42 MW solar generation project located in Lunenburg County, Virginia. The development project is being pursued by Oriden LLC and would connect to the electric grid within the service territory of Dominion. The project's point of interconnection is identified as the Gary 25 kV facility, from which the project takes its name.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1889, with a queue entry date of April 27, 2026. It is currently in active status and is being evaluated as part of PJM's C01 study phase under a Generation Interconnection service request. The proposed commercial operation date for the project is October 31, 2030. As of the latest available data, no interconnection agreement status has been reported for the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Lunenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Oriden LLC
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Gary 25 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- POI Substation
- Gary Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.