Plano 345 kV
250 MW storage in Gallatin, IL · In queue since April 2026 · Proposed COD September 2030
250 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-30
Plano 345 kV (queue ID PJM-C01-1778) is a proposed 250 MW battery energy storage development project in Gallatin County, Illinois. The project is being developed by ENGIE IR Holdings LLC and would be located within the service territory of the utility ComEd. It is designed to connect to the grid at the Plano 345 kV point of interconnection, from which the project takes its name.
The project is listed as active in the interconnection queue administered by PJM Interconnection, the regional transmission organization. It entered the queue on April 25, 2026, under a Generation Interconnection service request. It is currently in study phase C01, reflecting PJM's cycle-based interconnection process, and the data does not indicate that an interconnection agreement has been executed. The developer has proposed a commercial operation date of September 30, 2030.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Gallatin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
ENGIE IR Holdings LLC
Utility
ComEd
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Plano 345 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 167 PLANO
- POI Substation
- Plano Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Plano 345 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.