Wempletown - Cherry Valley 345 kV
300 MW generation in Boone, IL · In queue since April 2026 · Proposed COD March 2031
300 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-14
The Wempletown - Cherry Valley 345 kV project is a proposed 300 MW wind generation development project located in Boone County, Illinois. The project is being developed by Kishwaukee Wind, LLC and would connect to the transmission system within the ComEd utility service territory. Its proposed point of interconnection is the Wempletown - Cherry Valley 345 kV transmission line, from which the project takes its name.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1771, with a queue entry date of April 27, 2026. It is requested as a Generation Interconnection service and is currently in active status, participating in PJM's Cycle 1 (C01) study phase. The developer has proposed a commercial operation date of March 14, 2031.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IL
County
Boone
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Kishwaukee Wind, LLC
Utility
ComEd
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Wempletown - Cherry Valley 345 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VALLEY4 230 KV SR_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Wempletown - Cherry Valley 345 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.