Blaine - Roanoke 138 kV
200 MW storage in Franklin, VA · In queue since April 2026 · Proposed COD September 2030
200 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-30
Blaine - Roanoke 138 kV is a proposed 200 MW battery energy storage development project located in Franklin County, Virginia. The project is being developed by ENGIE IR Holdings LLC and would connect to the transmission system of AEP at the Blaine - Roanoke 138 kV point of interconnection. It is classified as a standalone storage project and has requested generation interconnection service.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1626, with a queue entry date of April 25, 2026. It is currently active and is being evaluated in PJM's C01 study phase. The proposed commercial operation date is September 30, 2030. The available data does not indicate an executed interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
ENGIE IR Holdings LLC
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Blaine - Roanoke 138 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Blaine - Roanoke 138 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.