Suffolk - Nucor Tap 230 kV
375 MW generation in Gates, NC · In queue since April 2026 · Proposed COD December 2030
375 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 8m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-01
The proposed project identified as Suffolk - Nucor Tap 230 kV (queue ID PJM-C01-1499) is a 375 MW solar-plus-battery hybrid generation development located in Gates County, North Carolina. Clenera DevCo, LLC is developing the project, which combines solar photovoltaic generation with energy storage. The interconnection data does not give separate capacities for the solar and storage components. The project takes its name from its proposed point of interconnection, the Suffolk - Nucor Tap 230 kV line, within the Dominion utility service territory.
The project is listed as active in the interconnection queue of PJM Interconnection, the regional transmission organization serving the area. It entered the queue on April 25, 2026, and is seeking Generation Interconnection service. It is being evaluated in PJM's C01 study phase, part of the organization's reformed cycle-based interconnection process. The proposed commercial operation date is December 1, 2030. The available data does not indicate the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NC
County
Gates
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Clenera DevCo, LLC
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Suffolk - Nucor Tap 230 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SUFFOLK 230 KV SR_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Suffolk - Nucor Tap 230 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.