Desoto - Tanners Creek 345 kV
101.501 MW generation in Randolph, IN · In queue since April 2026 · Proposed COD April 2026
101.501 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
<1 month
Schedule
6 months past proposed COD
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-27
The Desoto - Tanners Creek 345 kV project (queue ID PJM-C01-1418) is a proposed 101.5 MW wind generation development project located in Randolph County, Indiana. The project is being developed by Headwaters Wind Farm II LLC and would connect to the transmission system owned by American Electric Power (AEP). Its proposed point of interconnection is the Desoto - Tanners Creek 345 kV transmission line, from which the project takes its name.
The project is in the interconnection queue administered by PJM Interconnection, where it is listed with an active status under the Generation Interconnection service type. It was entered into the queue on April 27, 2026, and is being evaluated in PJM's C01 study phase. The queue record lists the same date, April 27, 2026, as its proposed commercial operation date. No interconnection agreement status is recorded for the project in the available data.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
HEADWATERS WIND FARM II LLC
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Desoto - Tanners Creek 345 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TANNERSC18 KV TC3
- POI Substation
- Tanners Creek
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.