Lordstown 345 kV
250 MW storage in Trumbull, OH · In queue since April 2026 · Proposed COD April 2029
250 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3 years
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-01
The Lordstown 345 kV project is a proposed 250 MW battery energy storage development project located in Trumbull County, Ohio. Developed by Lighthouse Mud Creek, LLC, the standalone storage project is planned to connect to the electric grid at the Lordstown 345 kV point of interconnection, within the service territory of ATSI (American Transmission Systems, Incorporated).
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1272, with a queue entry date of April 27, 2026. It is seeking Generation Interconnection service and is currently active in the C01 study phase, part of PJM's reformed cycle-based interconnection process. The proposed commercial operation date is April 1, 2029. The provided data does not indicate that an interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OH
County
Trumbull
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Lighthouse Mud Creek, LLC
Utility
ATSI
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Lordstown 345 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LRDTWNEC19 KV CT11
- POI Substation
- Lordstown Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Lordstown 345 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.