Coolwell Switch - Wallon 12.47 kV
3 MW generation in Amherst, VA · In queue since April 2026 · Proposed COD January 2028
3 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 9m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-30
Coolwell Switch - Wallon 12.47 kV (queue ID PJM-C01-1254) is a proposed 3 MW solar generation project in Amherst County, Virginia. The development project is being pursued by Partridge Creek Solar, LLC and would connect to the electric system at the Coolwell Switch - Wallon 12.47 kV point of interconnection, within the service territory of AEP. The project is a standalone solar facility and has no battery storage or other hybrid components.
The project is listed as active in the PJM Interconnection queue, where it entered on April 27, 2026, under a generation interconnection service request. It is being evaluated in PJM's C01 study phase, part of the regional transmission organization's cycle-based interconnection process. The developer has proposed a commercial operation date of January 30, 2028. The available data does not indicate whether an interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
VA
County
Amherst
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Partridge Creek Solar, LLC
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Coolwell Switch - Wallon 12.47 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Coolwell Switch - Wallon 12.47 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.