Homer City 230 kV
780 MW generation in Indiana, PA · In queue since March 2026 · Proposed COD November 2029
780 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
Homer City 230 kV is a proposed natural gas-fired generation project located in Indiana County, Pennsylvania. The development project, sponsored by Homer City Generation, L.P., has a total proposed capacity of 780 MW. It would connect to the grid at the Homer City 230 kV point of interconnection, within the service territory of PENELEC.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1250 and entered the queue on March 24, 2026. It is designated as a Generation Interconnection request and is currently in study phase C01, with an active status. The proposed commercial operation date is November 1, 2029. The available data do not indicate the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Indiana
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Homer City Generation, L.P.
Utility
PENELEC
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Homer City 230 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HOMERCIT230 KV PIERCE N
- POI Substation
- Homer City Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Homer City 230 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.