Warren County 500 kV (PJM-C01-1242) — Project Summary

Queue ID
PJM-C01-1242
Capacity
11 MW
Technology
Gas
Status
active
Location
Warren, VA
Region
PJM
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
IA Status
—

Warren County 500 kV

PJM-C01-1242BetaActiveNatural GasPJMlive-pjm_cycle

11 MW generation in Warren, VA · In queue since April 2026 · Proposed COD April 2026

BA: PJMISO/RTO: PJMNERC: SERCRC: PJM

11 MW

Capacity

0

Components

6 months

In Queue

—

IA Status

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

4 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

<1 month

Schedule

6 months past proposed COD

Study Phase

C01

Pre-Study0%
Queue EntryApr 24, 2026

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-27

About

Warren County 500 kV (queue ID PJM-C01-1242) is a proposed natural gas generation project located in Warren County, Virginia. The development project is sponsored by Virginia Electric and Power Company, which does business as Dominion Energy Virginia, and has a total proposed capacity of 11 MW. The project would connect to the transmission system in the Dominion utility zone at the Warren County 500 kV point of interconnection.

The proposed project is listed as active in the interconnection queue administered by PJM Interconnection, the regional transmission organization. It entered the queue on April 24, 2026, under the Generation Interconnection service type, and is being evaluated in the C01 study phase. The proposed commercial operation date is April 27, 2026. The queue data does not indicate the status of an interconnection agreement for the project.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

VA

County

Warren

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)

Utility

Dominion

Entity

PJM

Service Type

Generation Interconnection

Point of Interconnection

Warren County 500 kV

Data Source

live-pjm_cycle

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
FRONTROY21 KV WARCOCT2

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Warren County 500 kV
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.