Spurlock - Meldahl Dam 345 kV
780 MW generation in Mason, KY · In queue since April 2026 · Proposed COD December 2031
780 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 8m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-31
The Spurlock - Meldahl Dam 345 kV project (queue ID PJM-C01-1227) is a proposed 780 MW natural gas-fired generation development project located in Mason County, Kentucky. The project is being developed by East Kentucky Power Cooperative, Inc., with EKPC serving as the associated utility. It is designed to connect to the electric grid at the Spurlock - Meldahl Dam 345 kV point of interconnection, from which the project takes its name.
The project is listed as active in the interconnection queue of PJM Interconnection, the regional transmission organization serving the area. It entered the queue on April 27, 2026, under a Generation Interconnection service request, and is currently in the C01 study phase. The proposed commercial operation date is December 31, 2031. The available data does not indicate whether an interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
KY
County
Mason
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
East Kentucky Power Cooperative, Inc.
Utility
EKPC
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Spurlock - Meldahl Dam 345 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MELDDAM 13.8 KV GEN_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Spurlock - Meldahl Dam 345 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.