Crosswicks 230 kV
158 MW storage in Burlington, NJ · In queue since April 2026 · Proposed COD April 2031
158 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5 years
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-04-30
Crosswicks 230 kV is a proposed battery energy storage development project in Burlington County, New Jersey. The project is being developed by Scarlet Oak Energy Center, LLC and has a total proposed capacity of 158 MW. It would connect to the transmission system at the Crosswicks 230 kV point of interconnection, in the service territory of the utility PSEG.
The project is listed under queue ID PJM-C01-1190 in the interconnection queue administered by PJM Interconnection, the regional transmission organization. It entered the queue on April 27, 2026, as a Generation Interconnection request and is currently in active status within the C01 study phase. The proposed commercial operation date is April 30, 2031. The available data does not indicate that an interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NJ
County
Burlington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Scarlet Oak Energy Center, LLC
Utility
PSEG
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Crosswicks 230 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CROSSWIC13 KV CROSS1SP
- POI Substation
- Crosswicks Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Crosswicks 230 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.