Fort Martin 500 kV
1,112.307 MW generation in Monongalia, WV · In queue since April 2026 · Proposed COD December 2031
1,112.307 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2031
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 8m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-31
Fort Martin 500 kV is a proposed natural gas generation project in Monongalia County, West Virginia. The development project is sponsored by Monongahela Power Company and has a total proposed capacity of 1,112.31 MW. It would connect to the transmission system at the Fort Martin 500 kV point of interconnection, within the service territory of the APS (Allegheny Power System) utility zone.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1143 and holds an active status. It entered the queue on April 24, 2026, and is being evaluated in the C01 study phase under a Generation Interconnection service request. The proposed commercial operation date is December 31, 2031. The available data does not report whether an interconnection agreement has been executed.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Monongalia
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Monongahela Power Company
Utility
APS
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Fort Martin 500 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FTMARTIN22 KV GEN 1
- POI Substation
- Fort Martin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Fort Martin 500 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.