George Washington 138 kV
735.54 MW generation in Marshall, WV · In queue since April 2026 · Proposed COD June 2030
735.54 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 2m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The George Washington 138 kV project is a proposed natural gas-fired generation development in Marshall County, West Virginia, with a total capacity of 735.54 MW. The project is being developed by Calpine Mid-Atlantic Development, LLC and is located within the service territory of the utility AEP. It is designed to connect to the grid at the George Washington 138 kV point of interconnection, from which the project takes its name.
The project is listed in the PJM Interconnection queue under queue ID PJM-C01-1085 and holds an active status. It entered the queue on April 13, 2026, and is seeking Generation Interconnection service. The project is currently in study phase C01 of PJM's interconnection process. Its proposed commercial operation date is June 1, 2030.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WV
County
Marshall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Calpine Mid-Atlantic Development, LLC
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
George Washington 138 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about George Washington 138 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.