Reed - Reed Tap #1 69 kV
19.445 MW generation in Northumberland, PA · In queue since November 2025 · Proposed COD September 2029
19.445 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 10m
Study Phase
C01
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-30
Reed - Reed Tap #1 69 kV (queue ID PJM-C01-1029) is a proposed solar generation project in Northumberland County, Pennsylvania. Developed by Wildcat Renewables, LLC, the development project has a total planned capacity of 19.44 MW. It would connect to the transmission system at the Reed - Reed Tap #1 69 kV point of interconnection, within the service territory of the utility PPL.
The project is in the interconnection queue administered by PJM Interconnection, the regional transmission organization. It entered the queue on November 6, 2025, under the Generation Interconnection service type. The project is currently active and participating in study phase C01, part of PJM's cycle-based interconnection process. Its proposed commercial operation date is September 30, 2029. The available data does not indicate the status of an interconnection agreement for the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
Wildcat Renewables, LLC
Utility
PPL
Entity
PJM
Service Type
Generation Interconnection
Point of Interconnection
Reed - Reed Tap #1 69 kV
Data Source
live-pjm_cycle
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Reed - Reed Tap #1 69 kVForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.