PJM-AI2-435
20 MW hybrid in Berks, PA · In queue since March 2023 · Proposed COD December 2026
20 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AI2-435 is a proposed 20 MW hybrid solar and battery project located in Berks County, Pennsylvania. The project consists of 20 MW of solar generation. It is listed in the PJM interconnection queue as of March 9, 2023, with a proposed commercial operation date of December 31, 2026.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the South Hamburg _x0013_ St. Peters Village 69 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Berks
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
South Hamburg _x0013_ St. Peters Village 69 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AI2-435Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.