PJM-AI2-149
67.2 MW generation in Hardin, OH · In queue since February 2023 · Proposed COD December 2023
67.2 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
10 months
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-24
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AI2-149 is a proposed solar generation project with a total capacity of 67.2 MW. The project is located in Hardin County, Ohio, and is interconnected within the PJM Interconnection region. The queue entry date is February 28, 2023, with a proposed commercial operation date of December 24, 2023. The interconnecting utility is AEP.
The interconnection agreement (IA) status for PJM-AI2-149 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hardin Switch 345 kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Hardin Switch 345 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AI2-149Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.