Project PJM-AI2-149 — Project Summary

Queue ID
PJM-AI2-149
Capacity
67.2 MW
Technology
Solar
Status
active
Location
Hardin, OH
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AI2-149

PJM-AI2-149BetaActiveSolarPJMLBNL + Live

67.2 MW generation in Hardin, OH · In queue since February 2023 · Proposed COD December 2023

BA: PJMISO/RTO: PJMNERC: RFCRC: PJM

67.2 MW

Capacity

1

Components

Solar

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

10 months

Schedule

29 months past proposed COD

In Study38%
Queue EntryFeb 28, 2023

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-24

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

PJM-AI2-149 is a proposed solar generation project with a total capacity of 67.2 MW. The project is located in Hardin County, Ohio, and is interconnected within the PJM Interconnection region. The queue entry date is February 28, 2023, with a proposed commercial operation date of December 24, 2023. The interconnecting utility is AEP.

The interconnection agreement (IA) status for PJM-AI2-149 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hardin Switch 345 kV. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

OH

County

Hardin

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Hardin Switch 345 kV

Data Source

LBNL + Live

Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No Ask reports yet for this entity.

Ask about Project PJM-AI2-149
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.