PJM-AI2-077
56 MW generation in Kankakee, IL · In queue since February 2023 · Proposed COD March 2023
56 MW
Capacity
1
Components
Wind
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1 month
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-16
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AI2-077 is a proposed 56 MW wind generation project located in Kankakee County, Illinois. The project, interconnecting with ComEd via the Kanakee 138 kV point of interconnection, entered the PJM interconnection queue on February 28, 2023. Its proposed commercial operation date is March 16, 2023, and the interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists of 56 MW of wind capacity. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kanakee 138 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AI2-077Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.