PJM-AI2-070
150 MW storage in Atlantic, NJ · In queue since February 2023 · Proposed COD March 2027
150 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AI2-070 is a proposed 150 MW battery storage project located in Atlantic County, New Jersey. The project, which consists entirely of battery storage, is in the PJM interconnection queue as of February 24, 2023, with a proposed commercial operation date of March 1, 2027. The interconnecting utility is AEC. Its interconnection agreement status is listed as "In Progress (unknown study)".
The project is sponsored within the queue by PJM. The point of interconnection is the Dorothy - Lewis 138 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NJ
County
Atlantic
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
Dorothy - Lewis 138 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AI2-070Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.