PJM-AI1-128
5 MW hybrid in Centre, PA · In queue since September 2022 · Proposed COD September 2024
5 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2 years
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-09
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AI1-128 is a proposed 5 MW hybrid solar and battery project located in Centre County, Pennsylvania. The project consists of 5 MW of solar generation. It is listed in the PJM interconnection queue as of September 8, 2022, with a proposed commercial operation date of September 9, 2024. The interconnection point of contact is the Milesburg 12.47 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The utility involved is APS. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Centre
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Milesburg 12.47 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MILESBUR230 KV T82
- POI Substation
- Milesburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AI1-128Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.