PJM-AH2-419
210 MW hybrid in Laporte, IN · In queue since March 2022 · Proposed COD December 2026
210 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AH2-419 is a proposed 210 MW hybrid solar and battery project located in Laporte County, Indiana. The project, which consists of 210 MW of solar generation, is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of December 31, 2026. The interconnection point is at the Reynolds - Olive 345 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Laporte
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Reynolds - Olive 345 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH2-419Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.