PJM-AH2-410
20 MW hybrid in KY · In queue since March 2022 · Proposed COD June 2025
20 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The proposed project PJM-AH2-410 is a 20 MW solar and battery hybrid project located in Kentucky within the PJM Interconnection region. The project, which consists of 20 MW of solar generation, is being developed within the East Kentucky Power Cooperative (EKPC) service area.
The project entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of June 1, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the New Castle 69 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
New Castle 69 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- New Castle Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH2-410Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.