17.816 MW generation in Caroline, MD · In queue since March 2022 · Proposed COD November 2023
17.816 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 8m
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-15
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PJM-AH2-370 is a proposed solar generation project with a total capacity of 17.82 MW. The project is located in Caroline County, Maryland, and is interconnected within the PJM Interconnection region, with Delmarva Power (DPL) as the utility. The queue entry date is March 10, 2022, and the proposed commercial operation date is November 15, 2023.
The interconnection agreement (IA) status for PJM-AH2-370 is currently "In Progress (unknown study)". The point of interconnection (POI) is the Church - Oil City 138 kV III substation.
Generated from interconnection queue and public data sources
State
MD
County
Caroline
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Church - Oil City 138 kV III
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PJM-AH2-370Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.